City of Barrie Is Investing $26M to Build a 3,500-Seat Stadium for Toronto FC II's 2028 Relocation

The City of Barrie is investing $26 million to construct a soccer-specific stadium with a permanent capacity of 3,500 seats at Dunlop Street West and Bradford Street, its project page says. Toronto FC II relocates there from the 2028-2029 season as Barrie MLS NEXT Pro, under a partnership the City, Maple Leaf Sports & Entertainment (MLSE), MLS NEXT Pro and Barrie Stadium Group announced on 14 Jul 2026.
Key facts
- The City lists expansion to over 6,500 seats for sporting events and 8,500 for concerts, plus a parking lot with 450 spots.
- The club's FAQ says Barrie MLS NEXT Pro "is owned by Maple Leaf Sports & Entertainment (MLSE), and commercially operated by Barrie Stadium Group."
- Peter Raco, President and CEO of Barrie Stadium Group, said the project was "going through site plan approval right now with the city," CP24 reported on 29 Sep 2026.
- The City lists the stadium among its municipal infrastructure projects, with the status "Upcoming" and an estimated completion of 2028.
The story

At Meridian Place, "over 1,000 supporters and community members gathered" for the announcement, the City says. A 17 Jul 2026 transaction note from Wildeboer Dellelce LLP, which acted for MLSE, says "MLSE entered into an agreement with Barrie Football Club Inc. for the relocation of Toronto FC II to the City of Barrie." The note states no financial terms.
The City's page ties the site to the Marshall Green report for Council, "which looked at the opportunity for a stadium near the waterfront and downtown." The club's Stadium page says the stadium "sits at the centre of Barrie's waterfront at the corner of Dunlop and Bradford streets."

"This investment in our community, alongside Maple Leaf Sports and Entertainment and Barrie Stadium Group's investment in the newly formed Barrie MLS NEXT Pro franchise, will not only allow for professional sports to grow in Barrie, but provide a pivotal community hub for our youth sports to compete and learn in." Alex Nuttall, Mayor of Barrie, in the City's release of 14 Jul 2026
CP24 reports that the priority season-ticket deposit program launched at 10 a.m. on Tuesday 29 Sep and that "more than 1,200 families have expressed interest in the team." It also reports that ground had not been broken; Peter Raco said the plan was to "start breaking ground in the spring 2027."
What the documents state
Capital stack: the City states a $26 million construction investment
The City's project page gives the $26 million as the City's investment and says the City is building the stadium "in partnership with" MLSE, MLS NEXT Pro and Barrie Stadium Group.
- The City says the stadium and partnership are "expected to generate approximately $57 million in annual economic impact."
Land and control: the City builds, Barrie Stadium Group supports development and operation
The City's pages describe the City as the builder and Barrie Stadium Group as its partner in development and operation.
- The City says "Barrie Stadium Group will support the City in developing and operating the new downtown stadium," led by Chairman Jamie Massie and President and CEO Peter Raco.
- The City says it is "investigating suitable locations to build a new habitat for the chimney swifts" under federal Species At Risk rules.
Governance: how the club's pages divide ownership and control
The club's Team & League page splits the roles.
- It says "Toronto FC will manage all sporting aspects of the Club, including players and coaching, along with ownership of the MLS NEXT Pro franchise."
- It says "Barrie MLS NEXT Pro will manage all commercial and operations of the Club."
Where sources differ
City project page, club homepage, FAQ, the 4 Aug 2026 release and the Stadium page.
| Item | Source | As printed |
|---|---|---|
| Location | City project page | "Dunlop Street West and Bradford Street in downtown Barrie" |
| Location | Club homepage | "Situated on Barrie's waterfront" |
| Capacity | City project page and club FAQ | 3,500 permanent; over 6,500 for sport; 8,500 for concerts |
| Capacity | Club release, 4 Aug 2026 | "3,500 to 4,500 permanent seats, expandable to 7,500 seats" |
| Capacity | Club Stadium page | "a permanent capacity of 3,500 seats and the ability to expand to over 8,500" |
Not yet in the public record
- No 2026 council report, resolution or agreement on the stadium appears in the open-session Council and General Committee minutes from 3 Jun to 4 Nov 2026 (eSCRIBE) or the 2026 mayoral directions and decisions, searched 14 Nov 2026; the City's page says the site builds on earlier work for Council, including the Marshall Green report.
- The City's project page and release do not state who will own the stadium or the site, the total construction cost, any contribution from MLSE or Barrie Stadium Group, or the City's terms with Barrie Stadium Group, as of 14 Nov 2026.
- No deposit amount or refund term appears in the club's 4 Aug release, FAQ or homepage, or CP24's report, as of 14 Nov 2026.
- The terms of MLSE's agreement with Barrie Football Club Inc. are not stated in the Wildeboer Dellelce note or the City release (searched 14 Nov 2026).
What to watch
- November 2026: the club's 4 Aug release says the remaining Founding Season Membership Deposit allocation goes to the general public, "subject to availability."
- Spring 2027: the club "expects to announce its official name, crest and colours."
- Spring 2027: groundbreaking, per Peter Raco's 29 Sep statement to CP24.
- 2028: the City's estimated completion; the club FAQ says "The stadium is scheduled to March 2028," as published.
- 2028-2029: Barrie MLS NEXT Pro's first season, per the City release.
Sources
- City of Barrie, "Barrie Stadium" (municipal infrastructure project page), accessed 14 Nov 2026 (barrie.ca)
- City of Barrie, "Toronto FC II Relocates to Barrie as City Unveils Canada's Newest Soccer Stadium," 14 Jul 2026 (barrie.ca)
- Barrie MLS NEXT Pro, "Frequently Asked Questions," accessed 14 Nov 2026 (barriemlsnextpro.ca)
- CP24 (Luke Simard), "Got your tickets? Future MLS NEXT PRO club releases priority season ticket deposits," 29 Sep 2026 (cp24.com)
- City of Barrie, City Council and General Committee agendas and minutes, 3 Jun to 4 Nov 2026 (eSCRIBE) (pub-barrie.escribemeetings.com)
- Wildeboer Dellelce LLP, "Wildeboer Dellelce acts for Maple Leaf Sports and Entertainment (MLSE) in the Relocation of Toronto FC II to the City of Barrie," 17 Jul 2026 (wildlaw.ca)
- Barrie MLS NEXT Pro, homepage, accessed 14 Nov 2026 (barriemlsnextpro.ca)
- Barrie MLS NEXT Pro, "Stadium," accessed 14 Nov 2026 (barriemlsnextpro.ca)
- Barrie MLS NEXT Pro, "Team & League," accessed 14 Nov 2026 (barriemlsnextpro.ca)
- City of Barrie, "Mayoral Decisions & Directions," accessed 14 Nov 2026 (barrie.ca)
- Barrie MLS NEXT Pro, "Barrie MLS NEXT Pro Opens Priority Access for Founding Season Memberships and Premium Experiences," 4 Aug 2026 (barriemlsnextpro.ca)